    2003 Milestones:
June » NSC Critical Design Review
  » NSC Propulsion System selected (letter contract)
  » USCGC METOMPKIN (#2) arrived for conversion to 123’
May » SRP Critical Design Review
  » MPA Analysis complete; (CASA 235-300M) selection confirmed
  » Release contract for conversion of 123’ Patrol Boats #2 and #3
April » Maritime Patrol Aircraft (MPA) Preliminary Design Review
  » VUAV Preliminary Design Review
March » NSC Preliminary Design Review
  » NSC Long Lead materials delivery task order released
  » Deliver Prototype Short Range Prosecutor (SRP) (Zodiac)
  » Logistics Information Management System (LIMS) Strategic Readiness Review
February » USCGC MATAGORDA arrived for conversion to 123’ – 02/ 2003
  » Integrated Baseline Reviews (CLIN audits) – 12/ 2002, February, March, June 2003
  » HITRON (AgustaWestland) lease signed under Deepwater
  » VUAV (BellHelicopter Textron) concept confirmed
January » 123’ Patrol Boat Production Readiness Review
  » System-of-Systems In-Process Review – 01/ 2003
     
    » 2002 | 2003 | 2004 | 2005